CompTIA
PK0-004 · Question #1009
PK0-004 Question #1009: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-004 to reveal the answer and full explanation for question #1009. The question stem and answer options stay visible for context.
Tools and documentation
Question
A new project manager has entered a project in progress. Upon looking at the project schedule, the project manager finds predecessors have not been set. Based on the schedule above which of the following predecessors can be inferred?
Options
- ATasks 2 and 4 have an FS predecessor of Task 1. Task 3 has an FS predecessor of Task 2.
- BTasks 2 and 4 have an FS predecessor of Task 1. Task 3 has an FS predecessor of Task 1 and 2.
- CTask 4 has an FS predecessor of Task 1. Task 3 has an FS predecessor of Tasks 1 and 2. Task 2
- DTasks 2 and 4 have an FS predecessor of Task 1. Task 3 has an FS predecessor of Task 2. Task
Unlock PK0-004 to see the answer
You've previewed enough free PK0-004 questions. Unlock PK0-004 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#project schedule#task dependencies#finish-to-start#predecessors