PK0-003 · Question #87

Which of the following components of a project charter include identifying important milestones of the project?

The correct answer is A. Key project deliverables. Key project deliverables are components of a project charter that often include identifying important milestones of the project.

Tools and documentation

Question

Which of the following components of a project charter include identifying important milestones of the project?

Options

  • AKey project deliverables
  • BHigh level assumptions
  • CIdentify stakeholders
  • DHigh level constraints

How the community answered

(30 responses)
  • A
    90% (27)
  • C
    3% (1)
  • D
    7% (2)

Why each option

Key project deliverables are components of a project charter that often include identifying important milestones of the project.

AKey project deliverablesCorrect

Key project deliverables often include specific products, services, or results that the project will produce, and these deliverables are frequently associated with important milestones that mark their completion or significant progress points. The project charter typically provides a high-level summary of these deliverables and their associated milestones.

BHigh level assumptions

High level assumptions are conditions or factors believed to be true for planning purposes, not project milestones.

CIdentify stakeholders

Identifying stakeholders is a separate section or element of a project charter, focusing on who is impacted by or can impact the project, not its milestones.

DHigh level constraints

High level constraints are limitations or restrictions that affect the project, such as budget or schedule limits, and do not represent milestones.

Concept tested: Project charter components - deliverables and milestones

Topics

#project charter#milestones#project deliverables