PK0-003 · Question #72

Which of the following is a component of a risk management plan?

The correct answer is B. RBS. A key component of a risk management plan is the Risk Breakdown Structure (RBS), which provides a hierarchical representation of potential project risks. This structure helps in systematically identifying and categorizing risks.

Tools and documentation

Question

Which of the following is a component of a risk management plan?

Options

  • ARAM
  • BRBS
  • CCOQ
  • DKPI

How the community answered

(46 responses)
  • A
    4% (2)
  • B
    93% (43)
  • D
    2% (1)

Why each option

A key component of a risk management plan is the Risk Breakdown Structure (RBS), which provides a hierarchical representation of potential project risks. This structure helps in systematically identifying and categorizing risks.

ARAM

RAM stands for Responsibility Assignment Matrix, which is used for assigning roles and responsibilities, not a component of a risk management plan.

BRBSCorrect

The Risk Breakdown Structure (RBS) is a hierarchical decomposition of identified project risks arranged by category and subcategory. It is a critical component of a risk management plan, providing a structured way to identify and manage risks across the project.

CCOQ

COQ stands for Cost of Quality, which is a concept used in quality management, not a direct component of a risk management plan.

DKPI

KPI stands for Key Performance Indicator, which is a measurable value that demonstrates how effectively a company is achieving key business objectives, and while related to project monitoring, it's not a direct component of a risk management plan itself.

Concept tested: Risk management plan components - RBS

Source: https://learn.microsoft.com/en-us/project/what-is-risk-management

Topics

#risk management plan#risk breakdown structure#project planning