PK0-003 · Question #68

Which of the following components would be included in a project charter? (Select TWO).

The correct answer is B. Key project deliverables D. High level cost estimates. A project charter typically includes key project deliverables and high-level cost estimates to define the project's initial scope and financial parameters.

Tools and documentation

Question

Which of the following components would be included in a project charter? (Select TWO).

Options

  • ACommunications plan
  • BKey project deliverables
  • CWork Breakdown Structure
  • DHigh level cost estimates
  • ESpecific project milestones

How the community answered

(46 responses)
  • A
    4% (2)
  • B
    93% (43)
  • C
    2% (1)

Why each option

A project charter typically includes key project deliverables and high-level cost estimates to define the project's initial scope and financial parameters.

ACommunications plan

A communications plan is a more detailed planning document developed after the project charter, outlining how and when project information will be exchanged, rather than a high-level component of the charter itself.

BKey project deliverablesCorrect

Key project deliverables are included in a project charter to clearly outline the main products, services, or results that the project is expected to produce, providing a high-level understanding of the project's scope.

CWork Breakdown Structure

A Work Breakdown Structure (WBS) is a detailed decomposition of project deliverables into smaller, manageable components, which is developed during the planning phase after the project charter is approved.

DHigh level cost estimatesCorrect

High level cost estimates are a crucial part of a project charter, offering an initial approximation of the financial resources required for the project, which helps in securing authorization and preliminary budget allocation.

ESpecific project milestones

Specific project milestones are typically detailed in the project schedule and planning documents, whereas the project charter focuses on high-level objectives and a summary timeline, not granular milestones.

Concept tested: Project charter components

Topics

#project charter#project initiation#project deliverables#cost estimation

Community Discussion

No community discussion yet for this question.