Quality assurance is performed during which phase of a project?

The correct answer is C. During the execution phase. Quality assurance is primarily conducted during the execution phase of a project to ensure that the processes being used will produce deliverables that meet specified quality standards.

Project life cycle phases

Question

Quality assurance is performed during which phase of a project?

Options

  • ADuring the controlling phase
  • BDuring both controlling and execution phase
  • CDuring the execution phase
  • DDuring the planning phase

How the community answered

(32 responses)
  • B
    3% (1)
  • C
    94% (30)
  • D
    3% (1)

Why each option

Quality assurance is primarily conducted during the execution phase of a project to ensure that the processes being used will produce deliverables that meet specified quality standards.

ADuring the controlling phase

While quality is controlled throughout the project, quality *assurance* specifically focuses on the *processes* during execution, distinct from the broader controlling phase which also monitors overall project performance.

BDuring both controlling and execution phase

Although quality control (monitoring specific results) happens throughout execution and controlling, quality *assurance* is specifically about the *process* of building quality into the work, which is active during execution.

CDuring the execution phaseCorrect

Quality assurance (QA) involves auditing the quality requirements and the results of quality control measurements to ensure that proper quality standards and operational definitions are being applied. This process predominantly occurs during the execution phase, as the project team performs the work, to ensure that the correct processes are followed to produce high-quality deliverables.

DDuring the planning phase

The planning phase involves defining the quality management plan and requirements, but the actual performance of quality assurance-auditing processes-occurs when the work is actively being performed.

Concept tested: Project quality management phases

Topics

#Quality assurance#Project execution#Project phases