PK0-003 · Question #411
The change control board has requested that a project manager evaluate the impact of a major change request that will affect the timetable of several work-packages. Which of the following actions shou
The correct answer is A. Create a modified version of the project schedule applying the critical path method.. To evaluate the impact of a major change request affecting work package timetables, the project manager must first create a modified schedule and apply the Critical Path Method.
Question
The change control board has requested that a project manager evaluate the impact of a major change request that will affect the timetable of several work-packages. Which of the following actions should the project manager undertake FIRST?
Options
- ACreate a modified version of the project schedule applying the critical path method.
- BCall a project team meeting to use combined expert judgment to accept or reject the change
- CCreate a Pareto chart for the outputs from the specific work-packages identified by the
- DCrash the schedule to meet the original deadlines.
How the community answered
(37 responses)- A81% (30)
- B3% (1)
- C11% (4)
- D5% (2)
Why each option
To evaluate the impact of a major change request affecting work package timetables, the project manager must first create a modified schedule and apply the Critical Path Method.
A major change affecting work package timetables necessitates understanding its impact on the overall project duration. Creating a modified project schedule and applying the Critical Path Method (CPM) will accurately determine the new critical path and potential delays.
Accepting or rejecting the change is a decision that occurs after evaluating its impact, not the initial evaluation step itself.
A Pareto chart is a quality management tool used to prioritize defects or causes, not for evaluating the schedule impacts of a change request.
Crashing the schedule is a technique to shorten project duration and is a response to a schedule change, not the initial method for evaluating the impact of a change request.
Concept tested: Change Request Impact Analysis, Critical Path Method
Topics
Community Discussion
No community discussion yet for this question.