PK0-003 · Question #412
By completing the lessons learned during project closure, the project manager can:
The correct answer is B. determine the reasons for the success or failure of a project.. By completing the lessons learned during project closure, the project manager can identify and document the factors contributing to the project's successes and failures for future reference.
Question
By completing the lessons learned during project closure, the project manager can:
Options
- Amodify the project budget.
- Bdetermine the reasons for the success or failure of a project.
- Cmanage stakeholder expectations.
- Ddetermine the critical path of the project schedule.
How the community answered
(37 responses)- A3% (1)
- B95% (35)
- C3% (1)
Why each option
By completing the lessons learned during project closure, the project manager can identify and document the factors contributing to the project's successes and failures for future reference.
Modifying the project budget is a planning or controlling activity that typically occurs before or during project execution, not a purpose of lessons learned during closure.
The primary purpose of lessons learned is to systematically capture knowledge gained throughout the project, including what went well, what went wrong, and why, directly helping to understand project success or failure.
Managing stakeholder expectations is an ongoing process throughout the project lifecycle, not a specific outcome of completing lessons learned during closure.
Determining the critical path is part of project schedule development and monitoring, which is completed well before the lessons learned process during project closure.
Concept tested: Project Closure - Lessons Learned Purpose
Topics