CompTIA
PK0-003 · Question #410
PK0-003 Question #410: Real Exam Question with Answer & Explanation
The correct answer is D: Document the risk in the risk register, accept it and refer to the agreed vendor contracts for. See the full explanation below for the reasoning.
Question
A team member on a project uncovers a minor risk with the quality of a purchased component. The team uses their combined expert judgment to determine that the risk to the deliverable is very low. Which of the following is the MOST likely action the project manager should take?
Options
- AIssue a change request to the change control board to select a different vendor from the
- BCall a project team meeting to discuss the risk and communicate the issue directly with the
- CContact the vendor and request a thorough review of the products architecture.
- DDocument the risk in the risk register, accept it and refer to the agreed vendor contracts for
Community Discussion
No community discussion yet for this question.