The schedule estimates for a particular work package that is underway were not properly considered and the timescales are too tight. Which of the following methods should the project manager select to

The correct answer is B. SPI and SV. When schedule estimates for an underway work package are too tight, the project manager should investigate performance using the Schedule Performance Index (SPI) and Schedule Variance (SV).

Project management concepts

Question

The schedule estimates for a particular work package that is underway were not properly considered and the timescales are too tight. Which of the following methods should the project manager select to investigate?

Options

  • APDM
  • BSPI and SV
  • CCPM
  • DIssues log

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    88% (22)
  • C
    8% (2)

Why each option

When schedule estimates for an underway work package are too tight, the project manager should investigate performance using the Schedule Performance Index (SPI) and Schedule Variance (SV).

APDM

PDM (Precedence Diagramming Method) is a technique for scheduling activity relationships during project planning, not for investigating performance issues on an underway work package.

BSPI and SVCorrect

Schedule Performance Index (SPI) and Schedule Variance (SV) are key Earned Value Management (EVM) metrics used to assess project schedule performance against the baseline, indicating efficiency and whether the project is ahead or behind schedule, which directly helps in investigating tight timescales.

CCPM

CPM (Critical Path Method) is used to determine the longest path and shortest project duration during planning and monitoring, but not specifically for investigating why initial estimates were too tight on an underway work package.

DIssues log

An issues log records specific problems that require resolution, but SPI and SV are diagnostic tools to quantify and investigate underlying schedule performance issues systematically.

Concept tested: Earned Value Management - Schedule Performance Analysis

Topics

#Earned Value Management (EVM)#Schedule Performance Index (SPI)#Schedule Variance (SV)