PK0-003 · Question #300
In a Gantt chart, how are milestones displayed?
The correct answer is A. An activity with zero day duration. Milestones in a Gantt chart are represented as significant events with a zero-day duration, often depicted by a diamond symbol.
Question
In a Gantt chart, how are milestones displayed?
Options
- AAn activity with zero day duration
- BAn activity with one day duration
- CActivity-on-node with a finish-to-finish precedence
- DEnd-to-end bar graph showing the time to complete a task
How the community answered
(23 responses)- A96% (22)
- B4% (1)
Why each option
Milestones in a Gantt chart are represented as significant events with a zero-day duration, often depicted by a diamond symbol.
In a Gantt chart, a milestone represents a significant point or event in the project lifecycle, such as a major deliverable completion or a phase gate. By definition, a milestone itself does not consume time or resources, so it is logically represented as an activity with a zero-day duration.
An activity with a one-day duration implies work is being performed over that day, which contradicts the nature of a milestone as a point in time.
Activity-on-node is a method for drawing project network diagrams, not a way to display milestones specifically within a Gantt chart, and finish-to-finish precedence describes a relationship between tasks, not a milestone itself.
An end-to-end bar graph is used to represent tasks with duration, showing the time span over which work is performed, whereas a milestone marks a discrete point in time.
Concept tested: Gantt chart components - Milestones
Source: https://learn.microsoft.com/en-us/training/modules/project-management-introduction/4-gantt-charts