PK0-003 · Question #274

A project scope document would include which of the following? (Select TWO).

The correct answer is B. Key performance indicators C. Assumptions. A project scope document outlines the boundaries and specific deliverables of a project. Key performance indicators (KPIs) measure project success, while assumptions document factors believed to be true for planning purposes.

Tools and documentation

Question

A project scope document would include which of the following? (Select TWO).

Options

  • AWBS
  • BKey performance indicators
  • CAssumptions
  • DRisk matrix
  • ENetwork diagram

How the community answered

(24 responses)
  • B
    96% (23)
  • E
    4% (1)

Why each option

A project scope document outlines the boundaries and specific deliverables of a project. Key performance indicators (KPIs) measure project success, while assumptions document factors believed to be true for planning purposes.

AWBS

A Work Breakdown Structure (WBS) decomposes project work into smaller, manageable components but is a detailed output derived from the scope, not typically the scope document itself.

BKey performance indicatorsCorrect

Key Performance Indicators (KPIs) are often included in the scope document or related planning documents to define how the project's success will be measured, linking directly to what the project aims to achieve and deliver.

CAssumptionsCorrect

Assumptions are critical for project planning as they are factors considered to be true, real, or certain without proof, and they directly influence the scope and planning process. Documenting assumptions clarifies the basis on which the project is planned and managed.

DRisk matrix

A risk matrix identifies and analyzes potential risks to the project, which is part of risk management, a separate but related planning area, not a direct component of the scope statement.

ENetwork diagram

A network diagram illustrates the dependencies between project activities and their sequence, belonging to schedule management, not the core content of the project scope definition.

Concept tested: Project scope document components

Topics

#scope document#project scope#assumptions#KPIs