PK0-003 · Question #263
Which of the following avenues would allow the project manager to communicate project expectations, general timelines, and roles and responsibilities?
The correct answer is A. Kick-off meeting. A project kick-off meeting serves as the primary forum for the project manager to formally communicate project expectations, general timelines, and roles and responsibilities to all stakeholders.
Question
Which of the following avenues would allow the project manager to communicate project expectations, general timelines, and roles and responsibilities?
Options
- AKick-off meeting
- BStakeholder analysis
- CCommunication plan
- DScope document
How the community answered
(15 responses)- A87% (13)
- C7% (1)
- D7% (1)
Why each option
A project kick-off meeting serves as the primary forum for the project manager to formally communicate project expectations, general timelines, and roles and responsibilities to all stakeholders.
A kick-off meeting gathers key stakeholders and team members to collectively review project objectives, establish expectations, outline general timelines, and clarify roles and responsibilities, ensuring everyone starts with a shared understanding and common goals.
Stakeholder analysis is a process for identifying stakeholders and understanding their interests, influence, and impact, not a method for communicating project expectations.
A communication plan outlines how information will be communicated, who will communicate it, and when, but it is a document, not the avenue itself for initial widespread communication.
A scope document defines what is and is not included in the project, but it is a written artifact and not the interactive forum for initial communication and discussion of expectations, timelines, and roles.
Concept tested: Project initiation and communication - Kick-off meeting purpose