A new team has been put together for a construction project. The project currently does not have a cost estimate but the company has done other builds similar to the one at task and needs the estimate

The correct answer is A. Analogous. For a construction project needing a quick cost estimate with similar past company builds, analogous estimating is the best approach.

Project management concepts

Question

A new team has been put together for a construction project. The project currently does not have a cost estimate but the company has done other builds similar to the one at task and needs the estimate at the end of the week. Which of the following approaches would be BEST to determine the cost?

Options

  • AAnalogous
  • BBottom up
  • CTop down
  • DExpert judgment

How the community answered

(29 responses)
  • A
    93% (27)
  • C
    3% (1)
  • D
    3% (1)

Why each option

For a construction project needing a quick cost estimate with similar past company builds, analogous estimating is the best approach.

AAnalogousCorrect

Analogous estimating uses parameters from previous, similar projects, like cost per square foot from past construction builds, to estimate the cost of the current project, making it efficient when detailed information is limited and deadlines are tight.

BBottom up

Bottom-up estimating requires detailed work breakdown structures and granular estimates, which is too time-consuming for a 'end of the week' deadline when no cost estimate currently exists.

CTop down

Top-down is a general category, and analogous is a specific, effective type of top-down estimating for this scenario, making it a better, more precise answer.

DExpert judgment

Expert judgment involves consulting individuals with expertise, which is a valuable input but not an estimating technique itself; it often informs other techniques like analogous or three-point estimating.

Concept tested: Project cost estimation techniques - Analogous estimating