nerdexam
CompTIA

PK0-003 · Question #143

Which of the following should the project charter include?

The correct answer is B. A project description. The project charter is a formal document that authorizes a project or phase and should include a high-level project description, among other key elements.

Tools and documentation

Question

Which of the following should the project charter include?

Options

  • AA risk register
  • BA project description
  • CA post-mortem analysis
  • DAn issues log

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    88% (23)
  • D
    4% (1)

Why each option

The project charter is a formal document that authorizes a project or phase and should include a high-level project description, among other key elements.

AA risk register

A risk register is a detailed document that identifies and analyzes specific project risks, which is developed later in the planning process, not as part of the initial, high-level project charter.

BA project descriptionCorrect

The project charter is created early in the project lifecycle and serves to formally authorize the project, providing a high-level overview including the project purpose, measurable objectives, high-level requirements, and typically a brief project description that defines what the project is about. It empowers the project manager with authority to apply organizational resources to project activities.

CA post-mortem analysis

A post-mortem analysis (or lessons learned) is performed at the end of a project or phase, not included in the initial project charter.

DAn issues log

An issues log is used to track and manage issues that arise during project execution, which is an operational document created after the project charter.

Concept tested: Project charter components

Source: https://www.projectmanager.com/blog/what-is-a-project-charter

Topics

#project charter#project initiation#project description

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice