nerdexam
PMI

PGMP · Question #72

A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?

The correct answer is C. Secondary risks. The correct term is 'secondary risks' (Choice C). Secondary risks are new risks that emerge directly as a result of implementing a risk response. For example, if you respond to a scheduling risk by adding overtime work, a new secondary risk might be team burnout. This is…

Program Risk Management

Question

A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?

Options

  • AReactionary risks
  • BChain risks
  • CSecondary risks
  • DIn flux risks

How the community answered

(53 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    91% (48)
  • D
    6% (3)

Explanation

The correct term is 'secondary risks' (Choice C). Secondary risks are new risks that emerge directly as a result of implementing a risk response. For example, if you respond to a scheduling risk by adding overtime work, a new secondary risk might be team burnout. This is distinct from 'residual risks,' which are risks that remain after a response is applied. The other choices - reactionary risks, chain risks, and in-flux risks - are not standard project or program management terms defined in PMI frameworks.

Topics

#Risk Management#Secondary Risks#Risk Responses

Community Discussion

No community discussion yet for this question.

Full PGMP Practice