PGMP · Question #71
Which of the following is NOT true regarding the program work breakdown structure (WBS)?
The correct answer is C. It defines all the work and only the required work for the program.. Choice C states that the Program WBS 'defines all the work and only the required work for the program,' which is NOT true for a Program WBS. A Program WBS is a high-level structure that decomposes the program into its component projects and program-level deliverables - it does no
Question
Which of the following is NOT true regarding the program work breakdown structure (WBS)?
Options
- AIt defines a program and groups the program's discrete work elements in a way that helps
- BIt subdivides the program deliverables to work packages that are linked to the activities within the
- CIt defines all the work and only the required work for the program.
- DIt subdivides the program deliverables to work packages that are linked to the activities within the
How the community answered
(32 responses)- A3% (1)
- B6% (2)
- C91% (29)
Explanation
Choice C states that the Program WBS 'defines all the work and only the required work for the program,' which is NOT true for a Program WBS. A Program WBS is a high-level structure that decomposes the program into its component projects and program-level deliverables - it does not capture every granular work activity. Defining all work down to work packages is the responsibility of individual project-level WBSs within the program. The 100% rule ('all work and only the work') applies fully at the project WBS level, not the program WBS level. Choices A, B, and D describe legitimate program WBS characteristics: grouping discrete work elements, and subdividing program deliverables into work packages linked to project activities.
Topics
Community Discussion
No community discussion yet for this question.