nerdexam
PMIPMI

PGMP · Question #71

PGMP Question #71: Real Exam Question with Answer & Explanation

The correct answer is C: It defines all the work and only the required work for the program.. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

Which of the following is NOT true regarding the program work breakdown structure (WBS)?

Options

  • AIt defines a program and groups the program's discrete work elements in a way that helps
  • BIt subdivides the program deliverables to work packages that are linked to the activities within the
  • CIt defines all the work and only the required work for the program.
  • DIt subdivides the program deliverables to work packages that are linked to the activities within the

Topics

#Program WBS#Scope Management#Program Planning#100% Rule

Community Discussion

No community discussion yet for this question.

Full PGMP PracticeBrowse All PGMP Questions