nerdexam
PMI

PGMP · Question #71

Which of the following is NOT true regarding the program work breakdown structure (WBS)?

The correct answer is C. It defines all the work and only the required work for the program.. Choice C states that the Program WBS 'defines all the work and only the required work for the program,' which is NOT true for a Program WBS. A Program WBS is a high-level structure that decomposes the program into its component projects and program-level deliverables - it does no

Program Life Cycle Management

Question

Which of the following is NOT true regarding the program work breakdown structure (WBS)?

Options

  • AIt defines a program and groups the program's discrete work elements in a way that helps
  • BIt subdivides the program deliverables to work packages that are linked to the activities within the
  • CIt defines all the work and only the required work for the program.
  • DIt subdivides the program deliverables to work packages that are linked to the activities within the

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    91% (29)

Explanation

Choice C states that the Program WBS 'defines all the work and only the required work for the program,' which is NOT true for a Program WBS. A Program WBS is a high-level structure that decomposes the program into its component projects and program-level deliverables - it does not capture every granular work activity. Defining all work down to work packages is the responsibility of individual project-level WBSs within the program. The 100% rule ('all work and only the work') applies fully at the project WBS level, not the program WBS level. Choices A, B, and D describe legitimate program WBS characteristics: grouping discrete work elements, and subdividing program deliverables into work packages linked to project activities.

Topics

#Program WBS#Scope Management#Program Planning#100% Rule

Community Discussion

No community discussion yet for this question.

Full PGMP Practice