PGMP · Question #70
You have identified several issues in your program and have assigned issue owners. What component of program management oversees issue resolution?
The correct answer is A. Program governance. Program governance provides the oversight framework that ensures issues are properly tracked, escalated when needed, and resolved within defined authority levels. It includes the governance board or committee that reviews unresolved or high-impact issues that exceed the program…
Question
You have identified several issues in your program and have assigned issue owners. What component of program management oversees issue resolution?
Options
- AProgram governance
- BProgram risk management
- CQuality assurance
- DIssue owner management
How the community answered
(19 responses)- A95% (18)
- B5% (1)
Explanation
Program governance provides the oversight framework that ensures issues are properly tracked, escalated when needed, and resolved within defined authority levels. It includes the governance board or committee that reviews unresolved or high-impact issues that exceed the program manager's authority to resolve alone. Program risk management deals with uncertain future events, not already-identified issues. Quality assurance focuses on process compliance and product quality. 'Issue owner management' is not a recognized PMI program management component - while issue owners are responsible for resolution, the governance structure provides the oversight.