nerdexam
PMI

PGMP · Question #48

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent

The correct answer is D. -$117,295. Schedule Variance (SV) = Earned Value (EV) − Planned Value (PV). Step 1 - EV = BAC × actual % complete = $2,345,900 × 0.30 = $703,770. Step 2 - PV = BAC × planned % complete = $2,345,900 × 0.35 = $821,065. Step 3 - SV = EV − PV = $703,770 − $821,065 = −$117,295. The negative resu

Program Lifecycle Management

Question

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, what is the schedule variance (SV) of this program?

Options

  • A-$85,230
  • B$821,065
  • C-$284,100
  • D-$117,295

How the community answered

(49 responses)
  • A
    4% (2)
  • B
    6% (3)
  • C
    14% (7)
  • D
    76% (37)

Explanation

Schedule Variance (SV) = Earned Value (EV) − Planned Value (PV). Step 1 - EV = BAC × actual % complete = $2,345,900 × 0.30 = $703,770. Step 2 - PV = BAC × planned % complete = $2,345,900 × 0.35 = $821,065. Step 3 - SV = EV − PV = $703,770 − $821,065 = −$117,295. The negative result confirms the program is behind schedule. Option B ($821,065) is simply the PV, not the SV. Option C (−$284,100) would result from an incorrect percentage or BAC calculation. Option A (−$85,230) does not correspond to any valid EVM formula applied to these numbers.

Topics

#Earned Value Management (EVM)#Schedule Variance (SV)#Program Performance Measurement#Program Financial Analysis

Community Discussion

No community discussion yet for this question.

Full PGMP Practice