nerdexam
PMIPMI

PGMP · Question #48

PGMP Question #48: Real Exam Question with Answer & Explanation

Sign in or unlock PGMP to reveal the answer and full explanation for question #48. The question stem and answer options stay visible for context.

Program Lifecycle Management

Question

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, what is the schedule variance (SV) of this program?

Options

  • A-$85,230
  • B$821,065
  • C-$284,100
  • D-$117,295

Unlock PGMP to see the answer

You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Earned Value Management (EVM)#Schedule Variance (SV)#Program Performance Measurement#Program Financial Analysis
Full PGMP PracticeBrowse All PGMP Questions