nerdexam
PMI

PGMP · Question #446

A program manager is identifying and verifying risks as outlined in the risk management plan. The results will be recorded in which of the following?

The correct answer is A. Risk register. The risk register is the central repository where all identified risks are documented, including their descriptions, probability, impact, priority, status, and assigned owners. When a program manager identifies and verifies risks, those results are recorded in the risk…

Program Life Cycle

Question

A program manager is identifying and verifying risks as outlined in the risk management plan. The results will be recorded in which of the following?

Options

  • ARisk register
  • BRisk monitoring and control
  • CRisk response planning
  • DRisk mitigation strategy

How the community answered

(29 responses)
  • A
    86% (25)
  • B
    3% (1)
  • C
    3% (1)
  • D
    7% (2)

Explanation

The risk register is the central repository where all identified risks are documented, including their descriptions, probability, impact, priority, status, and assigned owners. When a program manager identifies and verifies risks, those results are recorded in the risk register. Options B, C, and D describe activities or strategies (monitoring and control, response planning, mitigation strategy) rather than documents where results are recorded. The risk register is the living document that captures and tracks risk information throughout the program lifecycle.

Topics

#Risk Management#Risk Register#Program Documentation#Program Lifecycle

Community Discussion

No community discussion yet for this question.

Full PGMP Practice