PGMP · Question #409

A new program manager joins a multi-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the…

The correct answer is D. Expected program benefits management plan. When stakeholders do not understand how a program will help the organization, the program benefits management plan is the most relevant document to present. It directly explains the expected benefits and how they will be delivered.

Benefits Management

Question

A new program manager joins a multi-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the organization. At the next stakeholder meeting, what should the program manager present to address their concerns?

Options

  • AProgram charter
  • BProgram scope assessment results
  • CBusiness and program roadmap
  • DExpected program benefits management plan

How the community answered

(63 responses)
  • A
    2% (1)
  • B
    6% (4)
  • C
    13% (8)
  • D
    79% (50)

Why each option

When stakeholders do not understand how a program will help the organization, the program benefits management plan is the most relevant document to present. It directly explains the expected benefits and how they will be delivered.

AProgram charter

The program charter authorizes the program and defines high-level objectives and constraints but does not provide the detailed benefits realization information stakeholders need.

BProgram scope assessment results

Program scope assessment results describe what work is included or excluded, not the organizational value or benefits the program will produce.

CBusiness and program roadmap

The business and program roadmap shows sequencing and timelines but does not explain in detail how the program's outcomes translate to organizational benefit.

DExpected program benefits management planCorrect

The expected program benefits management plan is correct because it explicitly documents what benefits the program is designed to deliver, how and when they will be realized, and the metrics for measuring them. Presenting this plan directly addresses stakeholder confusion about the program's organizational value and purpose.

Concept tested: Program benefits management plan stakeholder communication

Source: https://www.pmi.org/pmbok-guide-standards/foundational/program-management

Topics

#Benefits Management#Stakeholder Management#Program Value#Program Documentation