nerdexam
PMI

PGMP · Question #352

Your company is evaluating two projects for consideration. Project A has a 40% probability of $69,000 US and a 60% probability of -$10,000 US. Project B has a 60% probability of $56,000 US and a 40% p

The correct answer is B. Project B. Expected Monetary Value (EMV) is calculated by multiplying each outcome's probability by its monetary value and summing the results; Project B yields a higher EMV.

Benefits Management

Question

Your company is evaluating two projects for consideration. Project A has a 40% probability of $69,000 US and a 60% probability of -$10,000 US. Project B has a 60% probability of $56,000 US and a 40% probability of -$15,000 US. Which of the projects would you select based on the greatest expected monetary value?

Options

  • AProject A
  • BProject B
  • CProject A and B are of even value
  • DThe expected monetary value is not high enough on either to make a selection

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    84% (32)
  • C
    3% (1)
  • D
    8% (3)

Why each option

Expected Monetary Value (EMV) is calculated by multiplying each outcome's probability by its monetary value and summing the results; Project B yields a higher EMV.

AProject A

Project A yields an EMV of only $21,600, which is lower than Project B's $27,600.

BProject BCorrect

Project B's EMV is (0.60 x $56,000) + (0.40 x -$15,000) = $33,600 - $6,000 = $27,600. Project A's EMV is (0.40 x $69,000) + (0.60 x -$10,000) = $27,600 - $6,000 = $21,600. Project B has the greater EMV at $27,600 versus $21,600, making it the preferred selection.

CProject A and B are of even value

The two projects are not equal in EMV; Project B exceeds Project A by $6,000.

DThe expected monetary value is not high enough on either to make a selection

Both projects have positive EMV values, so a selection can and should be made based on the higher value.

Concept tested: Expected Monetary Value (EMV) calculation for project selection

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Expected Monetary Value (EMV)#Quantitative Risk Analysis#Project Selection#Financial Modeling

Community Discussion

No community discussion yet for this question.

Full PGMP Practice