nerdexam
PMI

PGMP · Question #354

The information technology system for the national power grid has been working well. Today, the main control processor crashed, disabling the west coast delivery of power to four states…

The correct answer is B. Fix the problem. When a risk response plan fails to fix an active problem causing harm, the immediate priority is to fix the problem before analyzing why the plan failed.

Program Risk Management

Question

The information technology system for the national power grid has been working well. Today, the main control processor crashed, disabling the west coast delivery of power to four states. Implementation of the risk response plan didn't fix the problem. Which of the following steps would they perform first?

Options

  • ADetermine why the risk response plan failed
  • BFix the problem
  • CDetermine why the problem happened
  • DAdjust the risk response plan

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    76% (22)
  • C
    3% (1)
  • D
    14% (4)

Why each option

When a risk response plan fails to fix an active problem causing harm, the immediate priority is to fix the problem before analyzing why the plan failed.

ADetermine why the risk response plan failed

Determining why the risk response plan failed is important but is a secondary activity performed after the immediate problem has been resolved.

BFix the problemCorrect

Fixing the problem is the first priority because power is currently out to four states, meaning ongoing harm is being caused to millions of people. Restoring functionality takes precedence over root-cause analysis or plan adjustments, which are secondary activities performed after the immediate crisis is resolved. This reflects the principle that operational continuity and safety always come before process review.

CDetermine why the problem happened

Determining why the problem happened is a root-cause analysis step that should follow, not precede, restoring the system to operation.

DAdjust the risk response plan

Adjusting the risk response plan is a post-recovery activity and cannot be the first step while the critical system remains down.

Concept tested: Risk response plan failure - operational recovery priority

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Incident Management#Risk Response#Crisis Management#Problem Resolution

Community Discussion

No community discussion yet for this question.

Full PGMP Practice