Risk Management
Question
The Project Manager and team are planning a banking software project. They are discussing what could go differently than planned on the project. They are also trying to identify warning signs that would show that these events could be on the verge of occurring. What are these warning signs called?
Options
- ARisk analysis
- BTriggers
- CProblem solving
- DRisks
Unlock PGMP to see the answer