PGMP · Question #353
The Project Manager and team are planning a banking software project. They are discussing what could go differently than planned on the project. They are also trying to identify warning signs that wou
The correct answer is B. Triggers. Warning signs that a risk event is about to occur are called triggers, also known as risk symptoms or warning signs in project risk management.
Question
The Project Manager and team are planning a banking software project. They are discussing what could go differently than planned on the project. They are also trying to identify warning signs that would show that these events could be on the verge of occurring. What are these warning signs called?
Options
- ARisk analysis
- BTriggers
- CProblem solving
- DRisks
How the community answered
(15 responses)- B93% (14)
- D7% (1)
Why each option
Warning signs that a risk event is about to occur are called triggers, also known as risk symptoms or warning signs in project risk management.
Risk analysis is the broader process of assessing risks, not the specific term for warning signs that a risk is about to occur.
Triggers are indicators that a risk event is imminent or has occurred, allowing the project team to activate the risk response plan proactively. Identifying triggers during risk planning enables the team to watch for specific warning signs, as described in the scenario where the team is discussing what signals would indicate a risk is 'on the verge of occurring.' This concept is a standard component of the Risk Register in the PMBOK framework.
Problem solving is a technique used after issues arise, not a term for warning signs of impending risk events.
Risks are the uncertain events themselves, not the warning signs that those events are about to happen.
Concept tested: Risk triggers and warning signs identification
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok