nerdexam
PMI

PGMP · Question #282

You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder's conference for 17 possible vendors. During the conference

The correct answer is C. Statement of work. After clarifications arise at a bidder's conference, the Statement of Work must be updated and redistributed to ensure all vendors bid on the same revised scope.

Program Lifecycle Management

Question

You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder's conference for 17 possible vendors. During the conference there were questions about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?

Options

  • ARequest for bid documents
  • BProposals
  • CStatement of work
  • DProgram management plan

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    15% (5)
  • C
    76% (25)
  • D
    6% (2)

Why each option

After clarifications arise at a bidder's conference, the Statement of Work must be updated and redistributed to ensure all vendors bid on the same revised scope.

ARequest for bid documents

Request for bid documents are not the artifact updated with conference clarifications - the SOW defining the work scope is what requires revision.

BProposals

Proposals are documents submitted by vendors to the buyer, not documents the program manager distributes to vendors.

CStatement of workCorrect

The Statement of Work defines the work scope that vendors bid on, and any clarifications affecting requirements or scope must be incorporated into an updated SOW and sent to all prospective vendors. This ensures fairness and accuracy across all bids. Distributing the updated SOW is a standard procurement integrity requirement following a bidder's conference.

DProgram management plan

The program management plan is an internal planning document and is not distributed to external vendors during the procurement process.

Concept tested: Updating procurement documents after bidder's conference

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Program Procurement#Statement of Work (SOW)#Bidder Conference#Vendor Management

Community Discussion

No community discussion yet for this question.

Full PGMP Practice