PGMP · Question #139

You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of…

The correct answer is A. Program transition plan. The program transition plan defines how the benefits and outputs of a program will be transferred from the program team to the operational units of the organization. It ensures continuity after the program closes.

Program Lifecycle Management

Question

You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?

Options

  • AProgram transition plan
  • BProgram closure plan
  • COperational transfer plan
  • DBenefits transfer plan

How the community answered

(31 responses)
  • A
    90% (28)
  • C
    6% (2)
  • D
    3% (1)

Why each option

The program transition plan defines how the benefits and outputs of a program will be transferred from the program team to the operational units of the organization. It ensures continuity after the program closes.

AProgram transition planCorrect

The program transition plan specifically documents the approach for transferring program deliverables, knowledge, and ongoing operational responsibility to the receiving organizational units, ensuring that the benefits produced by the program are sustainably integrated into day-to-day operations after program closure.

BProgram closure plan

The program closure plan addresses the administrative and procedural steps required to formally close the program, not the specific mechanism for transferring benefits to ongoing operations.

COperational transfer plan

Operational transfer plan is not a standard named plan within the PMI program management framework; the recognized term for this purpose is the program transition plan.

DBenefits transfer plan

Benefits transfer plan is not a formally defined plan in the PMI Standard for Program Management; the standard document for transferring program outputs to operations is the program transition plan.

Concept tested: Program transition plan for benefits transfer to operations

Source: https://www.pmi.org/pmbok-guide-standards/foundational/program-management

Topics

#Program Planning#Program Transition#Benefit Realization#Program Management Plans