Microsoft
MB-335 · Question #112
A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management. The company requires that employees register time against each machine on the shop floor. You need to…
The correct answer is A. time registration workers C. machines as a resource. https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/time-attendance-
Configure production prerequisites
Question
A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management. The company requires that employees register time against each machine on the shop floor. You need to configure the system so that employees can register time. Which two configurations must be set up? Each answer represents a partial solution. NOTE: Each correct selection is worth one point.
Options
- Atime registration workers
- Bregistration workflow
- Cmachines as a resource
- Delectronic timecard parameter
How the community answered
(48 responses)- A85% (41)
- B6% (3)
- D8% (4)
Explanation
https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/time-attendance-
Topics
#time and attendance#time registration workers#resource configuration#shop floor
Community Discussion
No community discussion yet for this question.