A company implements Dynamics 365 Supply Chain Management. Due to increased demand and limited space in the work cell area for product L0050, you must subcontract overflow work to another company…

The correct answer is A. Create a resource and work cell resource group for the subcontractor. B. Modify the overflow work operation and associate it with the subcontractor. C. Create transfer activities and assign them to the subcontractor. You've hit your limit · resets 4am (America/New_York)

Implement additional supply chain management features

Question

A company implements Dynamics 365 Supply Chain Management. Due to increased demand and limited space in the work cell area for product L0050, you must subcontract overflow work to another company. You have the following requirements:

  • Locate a warehouse at the subcontractor building.
  • Support picking and shipping activity tracking.
  • Associate costs of transporting materials between the locations in

the cost of the finished product. You need to modify the production flow. Which three actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.

Options

  • ACreate a resource and work cell resource group for the subcontractor.
  • BModify the overflow work operation and associate it with the subcontractor.
  • CCreate transfer activities and assign them to the subcontractor.
  • DModify the overflow work activity and assign it to the subcontractor.
  • ECreate a new production flow version.

How the community answered

(57 responses)
  • A
    42% (24)
  • D
    39% (22)
  • E
    19% (11)

Explanation

You've hit your limit · resets 4am (America/New_York)

Topics

#lean manufacturing#subcontracting#production flow#transfer activities

Community Discussion

No community discussion yet for this question.

Full MB-335 Practice