Microsoft
MB-335 · Question #62
You use the master planning module for Dynamics 365 Supply Chain Management. Planned production orders have been created. Several sales orders are canceled in response to concerns about recent…
The correct answer is C. Decrease. https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/action-messages
Implement additional supply chain management features
Question
You use the master planning module for Dynamics 365 Supply Chain Management. Planned production orders have been created. Several sales orders are canceled in response to concerns about recent online reviews of a product. You need to enable the appropriate action message. Which action message should you enable?
Options
- AIncrease
- BPostpone
- CDecrease
- DDerived actions
- EAdvance
How the community answered
(58 responses)- A12% (7)
- B2% (1)
- C79% (46)
- D2% (1)
- E5% (3)
Explanation
https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/action-messages
Topics
#action messages#master planning#demand changes#planned orders
Community Discussion
No community discussion yet for this question.