MB-335 · Question #99
A company uses the asset management module in Dynamics 365 Supply Chain Management. The company has four conveyer systems in the warehouse. A robotic crane moves pallets of products to the conveyer…
The correct answer is B. Update the work order lifecycle state. C. Calculate capacity load with the level field set to 0. You've hit your limit · resets 4am (America/New_York)
Question
A company uses the asset management module in Dynamics 365 Supply Chain Management. The company has four conveyer systems in the warehouse. A robotic crane moves pallets of products to the conveyer line. Each robotic crane and conveyer line is considered a multilevel asset. A work order arrives for a conveyer system. A technician completing the work order observes that the robotic crane needs a repair. The technician is not qualified to work on the robotic crane. You need to ensure that the robotic crane is repaired. Which two options should you configure? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.
Options
- ACreate a manual work order.
- BUpdate the work order lifecycle state.
- CCalculate capacity load with the level field set to 0.
- DCalculate capacity load with the level field set to 1.
- ECreate a related work order.
How the community answered
(29 responses)- A3% (1)
- B76% (22)
- D7% (2)
- E14% (4)
Explanation