MB-335 · Question #98
A company uses Dynamics 365 Supply Chain Management. Equipment installations in multiple regional locations require monthly maintenance. Two maintenance technicians have holiday time off scheduled…
The correct answer is B. Job scheduling. You've hit your limit · resets 4am (America/New_York)
Implement additional supply chain management features
Question
A company uses Dynamics 365 Supply Chain Management. Equipment installations in multiple regional locations require monthly maintenance. Two maintenance technicians have holiday time off scheduled this month. You need to ensure that all scheduled work orders are completed within the month around the holiday schedules. Which feature should you use?
Options
- AActivity-based subcontracting
- BJob scheduling
- CCapacity load calculation
- DOperations scheduling
- EPlanning optimization
How the community answered
(36 responses)- A8% (3)
- B86% (31)
- C3% (1)
- E3% (1)
Explanation
You've hit your limit · resets 4am (America/New_York)
Topics
#job scheduling#maintenance work orders#capacity planning#holiday scheduling