MB-335 · Question #113

You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar. A machine in the facility is defective and…

The correct answer is A. Navigate to the resource. Configure a calendar deviation to set the calendar to closed for the next. You've hit your limit · resets 4am (America/New_York)

Configure production prerequisites

Question

You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar. A machine in the facility is defective and must be closed for repairs for the next two days. You need to configure the resource calendar to close the resource for production for the next two days. What should you do?

Options

  • ANavigate to the resource. Configure a calendar deviation to set the calendar to closed for the next
  • BNavigate to the calendar used for production and close the next two days.
  • CNavigate to the resource. Change the calendar to closed on the resource.
  • DNavigate to the resource group. Change the calendar to closed on the resource group.

How the community answered

(24 responses)
  • A
    92% (22)
  • B
    4% (1)
  • D
    4% (1)

Explanation

You've hit your limit · resets 4am (America/New_York)

Topics

#resource calendar#calendar deviation#production resource#capacity