You are the lead product design manager at a Process manufacturing plant. A formula that produces egg yolks as a by-product. This by-product is added back into inventory at standard cost and can be…

The correct answer is A. Per series. https://learn.microsoft.com/en-us/dynamics365/supply-chain/cost-management/methodology- total-cost-allocation

Implement production methods

Question

You are the lead product design manager at a Process manufacturing plant. A formula that produces egg yolks as a by-product. This by-product is added back into inventory at standard cost and can be used in other production batches. You need to select the by-product cost allocation. Which cost allocation type should you use?

Options

  • APer series
  • BPercent
  • CRecycled
  • DPer quantity

How the community answered

(57 responses)
  • A
    82% (47)
  • B
    9% (5)
  • C
    4% (2)
  • D
    5% (3)

Explanation

https://learn.microsoft.com/en-us/dynamics365/supply-chain/cost-management/methodology- total-cost-allocation

Topics

#process manufacturing#by-product#cost allocation#formula