MB-335 · Question #115
A company uses Dynamics 365 Supply Chain Management for Process manufacturing. You are reviewing the planned production orders for the next two weeks. There are several production orders for the…
The correct answer is D. Rerun master planning. Select the static plan with a coverage time fence of two weeks. https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/deprecated-master- plans#types-of-planning-methods
Question
A company uses Dynamics 365 Supply Chain Management for Process manufacturing. You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order. You need to optimize the planned production orders. What should you do?
Options
- AIn Planned orders, combine the production orders.
- BRerun master planning. Select the dynamic plan with a coverage time fence of two weeks.
- CFirm the orders.
- DRerun master planning. Select the static plan with a coverage time fence of two weeks.
How the community answered
(46 responses)- A4% (2)
- B11% (5)
- C2% (1)
- D83% (38)
Explanation
https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/deprecated-master- plans#types-of-planning-methods
Topics
Community Discussion
No community discussion yet for this question.