A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management. Break times are paid. The cost of a break time must be charged at the pay rate of the job in progress when…

The correct answer is A. Set Production Order Cost Category to Yes. B. Set Direct Payroll Cost Standard Time to Yes. https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/pay-based-on-

Configure production prerequisites

Question

A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management. Break times are paid. The cost of a break time must be charged at the pay rate of the job in progress when the break starts. You need to configure the break times to charge against the job in progress. Which two actions should you perform? Each answer presents a partial solution. NOTE: Each correct selection is worth one point.

Options

  • ASet Production Order Cost Category to Yes.
  • BSet Direct Payroll Cost Standard Time to Yes.
  • CSet Direct Payroll Cost Standard Time to Allocate.
  • DSet Production Order Cost Category to No.
  • ESet Direct Payroll Cost Standard Time to No.

How the community answered

(29 responses)
  • A
    72% (21)
  • C
    7% (2)
  • D
    14% (4)
  • E
    7% (2)

Explanation

https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/pay-based-on-

Topics

#time and attendance#break time#pay rate#cost category