You configured Dynamics 365 Field Service for a construction company. The company needs the ability to create a bookable resource to send a group of individuals with different skillsets, along with…

The correct answer is C. Crew. Resource crews allow dispatchers to search and schedule multiple resources at once. Resource crews can include a group of employees, subcontractors, equipment, facilities, or any combination thereof who will perform the same work during a period of time. Crews speed up and…

Schedule and dispatch work orders

Question

You configured Dynamics 365 Field Service for a construction company. The company needs the ability to create a bookable resource to send a group of individuals with different skillsets, along with building equipment, to the construction site to perform construction work for a period of two months. When you create a bookable resource record, what should you set as the resource type?

Options

  • AResource Group
  • BUser
  • CCrew
  • DPool

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    16% (6)
  • C
    71% (27)
  • D
    8% (3)

Explanation

Resource crews allow dispatchers to search and schedule multiple resources at once. Resource crews can include a group of employees, subcontractors, equipment, facilities, or any combination thereof who will perform the same work during a period of time. Crews speed up and simplify the scheduling process and allow team members to work together more consistently. https://learn.microsoft.com/en-us/dynamics365/field-service/resource-crews https://learn.microsoft.com/en-us/dynamics365/field-service/set-up-bookable-resources

Topics

#bookable resource#crew#resource type#group scheduling