Microsoft
MB-240 · Question #48
MB-240 Question #48: Real Exam Question with Answer & Explanation
The correct answer is C. Use Resource Crew Scheduling. A group of resources will work together for a set number of days, weeks, or months. https://docs.microsoft.com/en-us/dynamics365/field-service/resource-crews
Question
You are a Dynamics 365 for Field Service administrator for a construction company. You need to schedule a work order for a group of resources that will work together for a set number of days, week, or months. How should you achieve the goal without scheduling the same requirements multiple times manually by using the schedule board (or with the schedule assistant)?
Options
- AUse Facility Scheduling
- BUse Multi-Resource Scheduling
- CUse Resource Crew Scheduling
- DUse Universal Resource Scheduling
Explanation
A group of resources will work together for a set number of days, weeks, or months. https://docs.microsoft.com/en-us/dynamics365/field-service/resource-crews
Community Discussion
No community discussion yet for this question.