nerdexam
Microsoft

MB-240 · Question #48

You are a Dynamics 365 for Field Service administrator for a construction company. You need to schedule a work order for a group of resources that will work together for a set number of days, week…

The correct answer is C. Use Resource Crew Scheduling. A group of resources will work together for a set number of days, weeks, or months. https://docs.microsoft.com/en-us/dynamics365/field-service/resource-crews

Schedule and dispatch work orders

Question

You are a Dynamics 365 for Field Service administrator for a construction company. You need to schedule a work order for a group of resources that will work together for a set number of days, week, or months. How should you achieve the goal without scheduling the same requirements multiple times manually by using the schedule board (or with the schedule assistant)?

Options

  • AUse Facility Scheduling
  • BUse Multi-Resource Scheduling
  • CUse Resource Crew Scheduling
  • DUse Universal Resource Scheduling

How the community answered

(31 responses)
  • A
    10% (3)
  • B
    16% (5)
  • C
    71% (22)
  • D
    3% (1)

Explanation

A group of resources will work together for a set number of days, weeks, or months. https://docs.microsoft.com/en-us/dynamics365/field-service/resource-crews

Topics

#crew scheduling#multi-resource scheduling#resource groups#multi-day bookings

Community Discussion

No community discussion yet for this question.

Full MB-240 Practice