MB-240 · Question #326
MB-240 Question #326: Real Exam Question with Answer & Explanation
The correct answer is C. Go to Requirement Details > Specify Pattern, select days for each resource, and then. Field Service, Schedule work over multiple days Requirements can be scheduled across multiple days and weeks. Dispatchers can schedule multi-day work in between existing bookings, by double-booking existing schedules, or as a continuous block of time. https://learn.microsoft.com/
Question
Options
- AUse the schedule assistant to specify resource availability and days for each resource separately.
- BAccess the resource pool to manually assign days to individual resources for the multi-day
- CGo to Requirement Details > Specify Pattern, select days for each resource, and then
- DUtilize the auto-schedule feature to automatically allocate specific days to each resource.
Explanation
Field Service, Schedule work over multiple days Requirements can be scheduled across multiple days and weeks. Dispatchers can schedule multi-day work in between existing bookings, by double-booking existing schedules, or as a continuous block of time. https://learn.microsoft.com/en-us/dynamics365/field-service/schedule-multi-day-work
Community Discussion
No community discussion yet for this question.