MB-240 · Question #326
A dispatcher for a restaurant equipment repair company has a requirement for a multi-day, multi- resource booking. They need to schedule specific resources for individual days within the resource's…
The correct answer is C. Go to Requirement Details > Specify Pattern, select days for each resource, and then. Field Service, Schedule work over multiple days Requirements can be scheduled across multiple days and weeks. Dispatchers can schedule multi-day work in between existing bookings, by double-booking existing schedules, or as a continuous block of time…
Question
Options
- AUse the schedule assistant to specify resource availability and days for each resource separately.
- BAccess the resource pool to manually assign days to individual resources for the multi-day
- CGo to Requirement Details > Specify Pattern, select days for each resource, and then
- DUtilize the auto-schedule feature to automatically allocate specific days to each resource.
How the community answered
(28 responses)- A18% (5)
- B7% (2)
- C71% (20)
- D4% (1)
Explanation
Field Service, Schedule work over multiple days Requirements can be scheduled across multiple days and weeks. Dispatchers can schedule multi-day work in between existing bookings, by double-booking existing schedules, or as a continuous block of time. https://learn.microsoft.com/en-us/dynamics365/field-service/schedule-multi-day-work