JK0-017 · Question #73

Which of the following would be MOST helpful in creating project roles and resource requirements?

The correct answer is C. Work Breakdown Structure. See the full explanation below for the reasoning.

Question

Which of the following would be MOST helpful in creating project roles and resource requirements?

Options

  • AResponsibility Assignment Matrix
  • BProject Charter
  • CWork Breakdown Structure
  • DHuman Resources Plan

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    15% (3)
  • C
    75% (15)
  • D
    5% (1)