A project manager is mapping out a project based upon the dependencies of the project activities. Which of the following would be BEST for this process? (Select TWO).
The correct answer is B. ADM C. PDM. See the full explanation below for the reasoning.
Question
A project manager is mapping out a project based upon the dependencies of the project activities. Which of the following would be BEST for this process? (Select TWO).
Options
- ACPM
- BADM
- CPDM
- DGantt
- EPERT
How the community answered
(34 responses)- A6% (2)
- B79% (27)
- D3% (1)
- E12% (4)