CompTIA
JK0-017 · Question #70
A project manager has been asked by a major stakeholder to modify the scope of a project in progress. Which of the following is the best FIRST step?
The correct answer is A. Assess the impact the change will have on the project. See the full explanation below for the reasoning.
Question
A project manager has been asked by a major stakeholder to modify the scope of a project in progress. Which of the following is the best FIRST step?
Options
- AAssess the impact the change will have on the project.
- BCall a meeting and ensure all stakeholders agree to the changes.
- CSubmit a change request to the PMO.
- DObtain written approval from the project sponsor and make the requested changes.
How the community answered
(18 responses)- A78% (14)
- B11% (2)
- C6% (1)
- D6% (1)
Community Discussion
No community discussion yet for this question.