JK0-017 · Question #63

A project manager has contracted with a landscaping service to complete the grounds work on a new building. The landscaper provides the project manager with the following costestimate: $150 per…

The correct answer is C. $5250. See the full explanation below for the reasoning.

Question

A project manager has contracted with a landscaping service to complete the grounds work on a new building. The landscaper provides the project manager with the following costestimate:

$150 per hour, estimated time to completion=40 hours The landscaper has completed 35 hours of work. Which of the following is the Earned Value of this portion of the project?

Options

  • A$750
  • B$3000
  • C$5250
  • D$6000

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    83% (25)
  • D
    10% (3)

Community Discussion

No community discussion yet for this question.