CompTIA
JK0-017 · Question #63
A project manager has contracted with a landscaping service to complete the grounds work on a new building. The landscaper provides the project manager with the following costestimate: $150 per…
The correct answer is C. $5250. See the full explanation below for the reasoning.
Question
A project manager has contracted with a landscaping service to complete the grounds work on a new building. The landscaper provides the project manager with the following costestimate:
$150 per hour, estimated time to completion=40 hours The landscaper has completed 35 hours of work. Which of the following is the Earned Value of this portion of the project?
Options
- A$750
- B$3000
- C$5250
- D$6000
How the community answered
(30 responses)- A3% (1)
- B3% (1)
- C83% (25)
- D10% (3)
Community Discussion
No community discussion yet for this question.