CompTIA
JK0-017 · Question #62
An organization has started a project to upgrade all computers in an organization. During the implementation phase of the project, the computer vendor notifies the project manager that the computer…
The correct answer is C. Delaying. See the full explanation below for the reasoning.
Question
An organization has started a project to upgrade all computers in an organization. During the implementation phase of the project, the computer vendor notifies the project manager that the computer systems are on backorder. The vendor anticipates delivery of the systems within five business days. Which of the following resource leveling techniques would be MOST appropriate in this scenario?
Options
- ACrashing
- BOptimizing
- CDelaying
- DFast tracking
How the community answered
(55 responses)- A9% (5)
- B2% (1)
- C85% (47)
- D4% (2)
Community Discussion
No community discussion yet for this question.