The project manager of a project that involves a system-wide computer update receives a report that some computers cannot be updated. Which of the following is a BEST practice?

The correct answer is D. Perform an impact analysis and contact the project sponsor. See the full explanation below for the reasoning.

Question

The project manager of a project that involves a system-wide computer update receives a report that some computers cannot be updated. Which of the following is a BEST practice?

Options

  • AContact the stakeholders in the project to determine the best course of action.
  • BComplete a project management change form without notifying the sponsor.
  • CDocument the change to the project without informing the stakeholders.
  • DPerform an impact analysis and contact the project sponsor.

How the community answered

(16 responses)
  • A
    6% (1)
  • C
    13% (2)
  • D
    81% (13)