JK0-017 · Question #59
The project manager of a project that involves a system-wide computer update receives a report that some computers cannot be updated. Which of the following is a BEST practice?
The correct answer is D. Perform an impact analysis and contact the project sponsor. See the full explanation below for the reasoning.
Question
The project manager of a project that involves a system-wide computer update receives a report that some computers cannot be updated. Which of the following is a BEST practice?
Options
- AContact the stakeholders in the project to determine the best course of action.
- BComplete a project management change form without notifying the sponsor.
- CDocument the change to the project without informing the stakeholders.
- DPerform an impact analysis and contact the project sponsor.
How the community answered
(16 responses)- A6% (1)
- C13% (2)
- D81% (13)