An organization has developed a project that will be taking place in a volatile climate. Which of the following aspects of the project plan will be affected, and what action should the project…

The correct answer is C. Risk management; create a risk matrix. See the full explanation below for the reasoning.

Question

An organization has developed a project that will be taking place in a volatile climate. Which of the following aspects of the project plan will be affected, and what action should the project manager take?

Options

  • AScope management; complete a communications plan
  • BCost management; prepare a budget analysis
  • CRisk management; create a risk matrix
  • DWork performance information; implement a WBS

How the community answered

(39 responses)
  • A
    15% (6)
  • B
    5% (2)
  • C
    72% (28)
  • D
    8% (3)