A key stakeholder sends an email to the project manager expressing dissatisfaction with the progress of the project. Which of the following would be the BEST way for the project manager to address…
The correct answer is D. Telephone the stakeholder to address the concerns. E. Have a face-to-face meeting with the stakeholder. See the full explanation below for the reasoning.
Question
A key stakeholder sends an email to the project manager expressing dissatisfaction with the progress of the project. Which of the following would be the BEST way for the project manager to address the stakeholder's concerns? (Select TWO).
Options
- AAsk the stakeholder to submit a change request.
- BSend the stakeholder an email.
- CSchedule a monthly conference call with the stakeholder.
- DTelephone the stakeholder to address the concerns.
- EHave a face-to-face meeting with the stakeholder
How the community answered
(57 responses)- A18% (10)
- B4% (2)
- C9% (5)
- D70% (40)