Question

Several stakeholders have asked the project manager to provide a weekly performance report. Which of the following may be the reason for the request?

Options

  • ATo notify the team that the project has started.
  • BTo provide needed criticism to poor team performers.
  • CTo monitor change requests.
  • DTo measure project progress.