CompTIA
JK0-017 · Question #483
The project charter is an output of which of the following project phases?
The correct answer is A. Initiation. See the full explanation below for the reasoning.
Question
The project charter is an output of which of the following project phases?
Options
- AInitiation
- BPlanning
- CExecution
- DClosing
How the community answered
(40 responses)- A80% (32)
- B13% (5)
- C3% (1)
- D5% (2)
Community Discussion
No community discussion yet for this question.