CompTIA
JK0-017 · Question #482
A project manager is informed that material expenditures will increase. Which of the following documents should be referenced to address this increase?
The correct answer is B. Cost management plan. See the full explanation below for the reasoning.
Question
A project manager is informed that material expenditures will increase. Which of the following documents should be referenced to address this increase?
Options
- AWork Breakdown Structure (WBS)
- BCost management plan
- CApproved project charter
- DProject scope document
How the community answered
(49 responses)- A2% (1)
- B78% (38)
- C12% (6)
- D8% (4)
Community Discussion
No community discussion yet for this question.