A project team member is uncertain how many activities are required to complete a task. Which of the following documents should be referenced?

The correct answer is C. Work Breakdown Structure (WBS). See the full explanation below for the reasoning.

Question

A project team member is uncertain how many activities are required to complete a task. Which of the following documents should be referenced?

Options

  • AKey Performance Indicators (KPIs)
  • BProject charter
  • CWork Breakdown Structure (WBS)
  • DStatement of Work (SOW)

How the community answered

(39 responses)
  • A
    13% (5)
  • B
    5% (2)
  • C
    79% (31)
  • D
    3% (1)