CompTIA
JK0-017 · Question #480
A project team member is uncertain how many activities are required to complete a task. Which of the following documents should be referenced?
The correct answer is C. Work Breakdown Structure (WBS). See the full explanation below for the reasoning.
Question
A project team member is uncertain how many activities are required to complete a task. Which of the following documents should be referenced?
Options
- AKey Performance Indicators (KPIs)
- BProject charter
- CWork Breakdown Structure (WBS)
- DStatement of Work (SOW)
How the community answered
(39 responses)- A13% (5)
- B5% (2)
- C79% (31)
- D3% (1)
Community Discussion