Which of the following is true of fast tracking a schedule?
The correct answer is B. Project activities will be performed concurrently. See the full explanation below for the reasoning.
Question
Which of the following is true of fast tracking a schedule?
Options
- AProject schedule critical path will change.
- BProject activities will be performed concurrently.
- CProject schedule is shortened by decreasing the project scope.
- DProject schedule lead times are increased.
How the community answered
(26 responses)- A15% (4)
- B69% (18)
- C12% (3)
- D4% (1)